Min of FMPWH presides over signing of 540MW Power Purchase Agreement ..

  • Post author:
  • Post category:TOP NEWS

….Black Rhino Group, Dangote Group, NNPC to build $1.1bn power plant

Oct 26, 2017

Ministry of  Federal Ministry of Power, Works and Housing. Abuja, Nigeria today presided over signing of 540MW Power Purchase Agreement between the Nigerian Bulk Electricity Trading Plc (NBET) is a Federal Government of Nigeria (FGN) owned public liability company  and Qua Iboe Independent Power Plant.

Emir of Kano, Emir Muhammadu Sanusi II (left) and Chairman/Managing Director, Mobil Producing Nigeria, Mr Paul McGrath(right) during the signing of the Qua Ibo Power Plant”s Power Purchase Agreement with NBET at the Ministry of Power, Works & Housing Headquarters in Mabushi, Abuja.   

 

Dangote Group, Black Rhino Group in collaboration with Nigerian National Petroleum Corporation (NNPC) have formalised agreement to construct  the Qua Iboe Power Plant (QIPP), in Akwa Ibom State, at the cost of $1.1 billion.

The investors group on Thursday October 2016 signed an MOU with Nigeria Bulk Electricity Trading Plc (NBET) to develop the project which would add 540 megawatts (mw) electricity to the nation’s grid by 2021.

The Minister of Power, Works and Housing, Mr Babatunde Fashola, who supervised the signing of the Power Purchase Agreement (PPA) in Abuja, said the development was part of government’s desire to consistently provide stable electricity in the country.

Part of the agreement was also the approval of a Put/Call Option Agreement (PCOA) by NBET and the Ministry of Finance along with the investors to guarantee the sales of electricity when the plant becomes operational.

Although the investors said they will build a 58km long transmission line to evacuate its output, Fashola assured that the Ikot Ekpene to Ikot Abasi transmission line built by the National Integrated Power Projects (NIPPs) would be ready to take power from the Qua Iboe plant.

The investors said Mobil Producing Nigeria (MPN) which initiated the power project with the NNPC, sold its rights to develop the project to QIPP investors. However, MPN has a 20-year Gas Sales Agreement (GSA) with the new investors to supply about 400 million standard cubic feet per day (mmscuf) of gas from its offshore oil production facility.

The Chairman of Black Rhino, and Emir of Kano, Muhammadu Sanusi II, said the conclusion of the PPA and PCOA processes would give promoters of the project the confidence to accelerate their Final Investment Decision (FID).

“Within the next months, we will achieve a financial closure to bring in about $1.2bn worth of direct investment into Nigeria. QIPP will utilise Nigeria’s gas resources to increase our electricity generation capacity and reduce the cost of power,” he said.

On her part, the Managing Director of NBET, Dr. Marilyn Amobi, said once the investors achieve a financial closure, they would start construction which should last between 18 to 24 months.

“We are just starting that now because Mobil decided to have its shares go to Black Rhino, and then we had to review the documents again because the original project was fully equity funded but now the structure has changed and it will now be debt and equity,” Amobi said, corroborating the MPN ownership transfer.